Lettering Removal – Macquarie Park

Scope of Works to be carried out:
  • Complete SWMS prior to commencement
  • Carry out works according to WHS standard
Saturday 1 – (adverse weather dependant)
  • Paint over AAO carpark lettering
  • Remove lettering by peeling and cleaning (razors unable to be used due to powder coating signage backing plates)
  • Razor removal of the signage at the security desk
  • Check measure for vinyl cover strips
Saturday 2 – (adverse weather dependant)
  • Access via EWP to meet high level building signage, informed by building manager as peelable vinyl lettering
  • Remove lettering by peeling and cleaning (razors unable to be used due to powder coating signage backing plates)
  • Fit vinyl cover strips (colour to match as close as possible)
  • No dealing with hazardous material has been allowed for, unless specifically mentioned above
  • Works to be completed outside business hours – Saturday
  • Leave site clean upon completion
  • Please Note: There is a possibility that letter shadowing may be left from removal